BTS Indoor Installation

BTS Indoor Installation, MBTS/BBU Site Indoor Installation and Commisioning,RFS/RRU Tower Top Mounted ,Commissioning, Integration & ATP Sign-Off.

 Un-packaging and Goods Verification and Shifting.
 Installation of BTS Rack.
 Power Cable and Grounding Cable routing and Terminate to MCB or IGB.
 E1 Cable Routing and Punching On DDF.
 Lightning Protection Box ,IGB,MCB,DDF Installation.
 Alarm Cable Routing and Environment Detection Sensor Fixed.
 RF Jumper Cable Connector Making
 RF Jumper Cable Routing and Connect to Existing Surge Arrestor.
 GPS Antenna Mount and cable routing.
 Installation for Cable Tray When it required.
 Labeling for all Cable and Sector.
 Prepare and Submit Hardware Installation Report.

BTS Outdoor Installation

Installation of Antenna Pole or RRU or MW? Pole, Hoisting of Antennas, Connectivity & Routing of Feeder Cables, Optical cable & Power Cable Routing

 3-Sectors Site Outdoor Antenna Mount.
 Feeder Cable Routing, Grounding and Termination.
 Surge Arrestor Installation and Grounding to OGB.
 OGB & Feeder Cable Windows Installation.
 Installation of Outdoor Cable Tray.
 Labeling For all Cable and Sector.